M65-B LEDs / Project Updates [M60/U80/THERMAL/NEMO/MK Accessories]

M65-B LED Video

Here’s a video of the M65-B ICED with our Heavy Industry keyset + LEDs on.
youtu.be/SkIlTayKC5k

L1040174.JPG
L1040191.JPG

EXTRA UNITS

We have extra units of the M65-B available on our website as part of the pre-order allocations in our manufacturing. These are in limited numbers and will no longer be available once exhausted.
ramaworks.store


PROJECT UPDATES

M60-A SEQ2

The contents of our container of M60-A units are arriving at our warehouse this Thursday or Friday - we’ll post an update when it does!

RW-M60-A-PRODUCT-RENDERS-SEQ2-EXPLODED-01.1515.jpg

U80-A

The machining for the U80 will finish this month! It will then move onto finish treatment; this includes: polishing, bead-blasting + surface treatment (Anodising / PVD). As each piece needs to be polished before it’s either bead-blasted or coated, it will take some time. We estimate it to finish production by the middle of February. Packaging & Logistics will also take a considerable amount of time given the number of units.

RW-U80-RENDER-A.1651.jpg

THERMAL

We estimate the THERMAL units to finish production at the end of February. Again, it will have to go considerable packaging and logistics before they ship. For both the U80 & THERMAL we estimate it will ship in Q1 of 2020.

RW-THERMAL-RENDER-01.1709.JPG

NEMO

NEMO will be completed machining this month, it will then move to the final processing. Note that this does not include the RW01 which will finish in Q1 of 2020. We will be shipping both NEMO and RW01 in Q1 - we’re working on some special packaging to include with each unit!

RW-KPL-CUBING-RENDER-CAR-A.1700-2.JPG

Camera Accessories

These should be shipping in February! They have finished manufacturing and will be assembled & packed when they arrive in our warehouse.

RW-MK-ACCESSORIES.1715.jpg